DEP Invites Comments On Renewal Of Title V Air Quality Permit For 165 MW Armstrong Power Natural Gas Power Plant In Armstrong County

The Department of Environmental Protection published notice in the October 24 PA Bulletin inviting comments on the renewal of a Title V Air Quality Permit for the 165 MW Armstrong Power natural gas power plant in South Bend Township, Armstrong County. (
PA Bulletin, page 6951)

No hearing has been scheduled, but one may be requested.

Comments are due November 23-- 30 days after this notice.

Comments and requests for a hearing should be sent to Mrs. Lori McNabb, Regional Air Quality Program Manager, Department of Environmental Protection, Northwest Region, 230 Chestnut Street, Meadville, PA 16335.  McNabb’s email is: lmcnabb@pa.gov. 

Copies of the application, the Department’s analysis and other documents used in the evaluation of the application are available for public inspection during normal business hours at the Department of Environmental Protection, 230 Chestnut Street, Meadville, PA 16335.

Requests to review the application should be made to: Matthew Williams, Facilities Permitting Chief, Air Quality Program, at (814) 332-6940. Williams’ email is: matwilliam@pa.gov. 

Read the entire PA Bulletin notice for more information. (PA Bulletin, page 6951)

For more information on environmental programs in Pennsylvania, visit DEP’s website.  Submit Environmental Complaints; Click Here to sign up for DEP’s newsletter; sign up for DEP’s eNotice; Like DEP on Facebook, Follow DEP on Twitter and visit DEP’s YouTube Channel.

[Posted: October 23, 2026]  PA Environment Digest