PUC Issues $875,000 Penalty In Settlement With Columbia Gas For 2019/2020 Natural Gas Pipeline Safety Violations In Allegheny, Washington Counties

On September 10, the Public Utility Commission approved a joint settlement with Columbia Gas of Pennsylvania Inc. related to past pipeline safety violations while completing main line replacement projects in Southwest Pennsylvania.

The Commission voted 5-0 to adopt the Recommended Decision of PUC Administrative Law Judge Jeffrey A. Watson – which recommended approval of a Joint Petition for Approval of Settlement filed on March 14, 2025, between the PUC’s Bureau of Investigation and Enforcement (I&E) and Columbia Gas. 

The PUC action resolves a formal complaint filed by I&E on Nov. 21, 2023, alleging that in 2019 and 2020 Columbia Gas and its contractor, Infrasource, violated state and federal regulations relating to visually unacceptable socket fusions along multiple main line replacement projects in Allegheny and Washington counties.  

Gas service line fusion is a permanent method of joining plastic polyethylene (PE) gas pipes using controlled heat to melt and blend the materials into a single, continuous piece.

I&E Investigation and Formal Complaint

In 2020, I&E launched an investigation as the result of a failed fusion at the company’s Tropical Avenue Project in Pittsburgh.  

Subsequent integrity validation digs at the Tropical Avenue Project, as well as at four additional Columbia Gas projects across Allegheny and Washington counties, discovered a much larger number of alleged violations related to fusion work, including--

-- Failure to identify no less than 220 visually unacceptable fusions and saddle tee fusions on service lines and main lines. These visually unacceptable fusions lacked a complete impression of the cold ring clamp and/or were mitered.

-- Failure to mark, label, or sign no less than 552 fusions according to Columbia Gas Standards.

-- Allowing an unqualified contractor employee to perform and inspect plastic fusions.

-- Failure to properly install no less than 44 saddle tee taps to a gas main line.

-- Failure to capture and maintain accurate records of the pipeline components and personnel performing work on the pipeline.

Following discovery of these safety violations, the settlement notes that during 2021 Columbia Gas completed replacement of all visually unacceptable fusions at the five locations and discontinued the use of socket fusion as a joining method. 

Settlement Terms and Conditions

Terms of the settlement between I&E and Columbia Gas include:

-- Payment of a $875,000 civil penalty, which will not be tax deductible nor passed through as an additional charge to Columbia Gas’ customers in Pennsylvania. In addition, the company may not recover the costs associated with the plastic fusion investigations and subsequent remediations for the projects identified in the formal complaint.

-- Implementation of corrective actions, to include replacement of all visually unacceptable fusions and designed to reduce risk associated with plastic pipe fusions, enhance contractor oversight, assure the production of quality fusions, and enhance knowledge of Columbia Gas’ system.

-- Amending company procedures to require the submission of a Facility Failure Report for all legacy production joints which are removed following a failure of a legacy plastic fusion visual inspection.

-- Development of a process to incorporate the findings and locations of visually unacceptable fusions removed from service into the annual Columbia Gas Distribution Integrity Management Program review.

-- Implementation of a fusion inspection documentation process to be used by Columbia Gas Construction Coordinators when evaluating fusions witnessed in the field.

-- Company notification to the PUC’s Pipeline Safety Division when a leak occurs at a plastic fusion as soon as practical, but not to exceed the next business day following discovery.

Columbia Gas is owned by NiSource and has approximately 448,000 customers in 26 counties across the Commonwealth.

Documents related to this case can be found at PUC Docket No.: C-2023-3044398.

Click Here for the PUC announcement.

Related Articles This Week - PUC:

-- PUC Moves To Address A.I. Data Center Impacts On Emergency Load Control Procedures, Allocation Of Costs Associated With Large Loads; Technical Conference On Cost Responsibility To Be Held  [PaEN] 

-- PUC Launches Review Of Utility Ratemaking, Working Group To Address Affordability, Transparency And Changing Economic Conditions  [PaEN]

-- PJM Interconnection Proposes Changes To Reliability Standards To Address Situations Where A.I. Data Centers Disconnect From The Grid Without Warning And Threaten Grid Stability  [PaEN]

-- PUC Issues $875,000 Penalty In Settlement With Columbia Gas For 2019/2020 Natural Gas Pipeline Safety Violations In Allegheny, Washington Counties  [PaEN] 

-- PA Oil & Gas Weekly Compliance Snapshot - September 5 to 11

     -- DEP: Tank Valve Failure Leads To 4,610 Gallon Spill Of Contaminated Water At XTO Energy Inc. Shale Gas Well Pad In Butler County  [PaEN]  

     -- DEP: Contaminated Water Misting Out Of Storage Tank, Fluid Spill At Expand Operating, LLC Shale Gas Well Pad In Bradford County  [PaEN] 

     -- DEP: Thick Orange Fluid Leaking From Storage Tank At Conventional Gas & Gas Well Site In Monroeville, Allegheny County  [PaEN]

     -- DEP Issues Violations To 7 More Conventional Oil & Gas Well Owners For Abandoning, Not Plugging Wells In 7 Counties  [PaEN]

     -- DEP: Complaint Investigation Finds Conventional Well Venting Gas In A Manner Posing A Safety Risk To Nearby Residence In Mercer County  [PaEN]

     -- DEP Finds Conventional Well Venting Gas During Investigation Of Leaking Conventional Gas Gathering Line In Unity Twp., Westmoreland County  [PaEN]   

     -- DEP: Drill Cuttings From Conventional Oil & Gas Well Improperly Spread Over Drill Site For Disposal In McKean County  [PaEN]  

-- DEP - Day 106: Ows Energy Inc. Failed To Cleanup Soil Contaminated By Water From Conventional Gas Well In Crawford County  [PaEN]  

     -- DEP: Pressure Testing Confirms Casing/Cementing Failures In 3 Expand Operating LLC Shale Gas Wells In Bradford County, Including One New Violation  [PaEN] 

     -- DEP Issued 2nd Round Of Major Erosion & Sedimentation Violations At Equitrans Water SVC (PA) [EQT] Jaybird Shale Gas Water Impoundment Restoration Site In Washington County  [PaEN] 

     -- DEP: Site Preparations For Plugging Diversified Production LLC Conventional Gas Well Results In Multiple Erosion & Sedimentation Violations In Fayette County  [PaEN] 

     -- PUC Issues $875,000 Penalty In Settlement With Columbia Gas For 2019/2020 Natural Gas Pipeline Safety Violations In Allegheny, Washington Counties  [PaEN] 

Related Articles This Week:

-- DEP Oil & Gas Technical Advisory Board Meets Sept. 16 To Hear Updates On New Methane Control Regulations; Federal Well Plugging Program; Other Issues  [PaEN]  

-- Governor's Budget Office Takes $138.5 Million From Act 13 Drilling Impact Fee, Marcellus Legacy Fund, Farmland Preservation Fund, Underground Storage Tank Insurance Fund To Balance State Budget  [PaEN]

NewsClips:

-- TribLive: Shell Petrochemical Plant To Pay $15 Million Settlement For Air Pollution Violations 

-- Pittsburgh Business Times: PA Natural Gas Production Drops For 2nd Straight Quarter

-- Reuters: Federal Court Vacates New Jersey Permit For Northeast Supply Enhancement Natural Gas Pipeline

[Posted: September 10, 2026]  PA Environment Digest

No comments :

Post a Comment

Subscribe To Receive Updates:

Enter your email address:

Delivered by FeedBurner