In a letter, the governors said--
"In July, we saw the staggering results of PJM’s capacity auction for the 2025/2026 Delivery Year, with clearing prices almost 10 times higher than the previous auction. These record high prices are a serious concern.
"The resulting $14.7 billion bill will be paid by our residents and our businesses and could deter future economic development.
"Alongside these high capacity auction prices, the underlying issues with the interconnection queue will delay new energy generation, leading to decreased competition in the market and even higher costs for the average consumer."
"We recognize supply has decreased while demand is projected to grow at an accelerated rate.
“However, both the Independent Market Monitor for PJM and the Organization of PJM States, Inc. (OPSI) have correctly observed that there are serious flaws with the PJM capacity market construct leading to capacity prices that fail to reflect supply and demand fundamentals."
The governors call for PJM to consider five changes--
-- Ensure that capacity from Reliability Must Run units is included in the next Base Residual Auction. OPSI, the Independent Market Monitor, and complainants all agree that making this change would save consumers between $3-5 billion without undermining market competitiveness or necessary price signals;
-- Eliminate the must-offer exemption for intermittent generation resources, while protecting them from performance penalties that discourage participation;
-- Lower the capacity price cap back to the level it was prior to PJM’s recent capacity market reforms;
-- Review the propriety of recent Effective Load Carrying Capability accreditation changes and adjust to improve accuracy; and
-- Although it may take longer than by the upcoming auction, swiftly implement a subannual capacity market designed to reduce risk on the transmission system.
"Analysts estimate that, without any of these changes, the upcoming auction could result in over $30 billion in costs to consumers for the 2026/2027 Delivery Year.” [This would be on top of the $14.7 billion increase from the most recent auction.]
“This would be far beyond what is needed to send a price signal encouraging new capacity, at the expense of our consumers."
“We welcome PJM’s decision to delay the 2025/2026 base residual auction in order to provide time for PJM and stakeholders to work through these critical issues, but delay alone is not enough.”
"We remain concerned that the current years-long PJM interconnection process severely limits the ability of high capacity prices to encourage the development of additional capacity.
"If developers cannot expect to get through the interconnection queue before a reasonably near-term delivery year, then additional energy projects cannot be deployed in time – no matter how high prices rise."
"We recognize the work that PJM has done to reform this process, and we encourage the PJM Board to maintain focus on further improvements.
"In particular, we look forward to engaging on PJM’s recently announced Reliability Resource Initiative and ensuring that any new capacity from diverse, clean sources is available as soon as possible, as well as identifying an appropriate role for states to help identify “shovel ready” projects for inclusion in the accelerated process."
"Urgent action is needed to prevent customers from paying billions more than is necessary to support the development of needed capacity, and to reform the interconnection queue so developers can promptly respond to prices by providing new supply.
"We expect PJM to address these issues on an expedited basis, after which we request that the PJM Board hold a special session to address our longer-term concerns."
Click Here for a copy of the letter.
NewsClip:
-- Utility Dive: 5 Governors Call For PJM Capacity Market Rule Changes To Reduce ‘Unnecessary’ Consumer Costs
Resource Links - Electric Grid:
-- Spotlight PA: No One Is Using $2.6 Billion Hydrogen, Natural Gas Tax Credit, Shapiro Wants To Rewrite The Law To Boost Electricity Production
PA Oil & Gas Industry Public Notice Dashboards:
-- PA Oil & Gas Industrial Facilities: Permit Notices, Opportunities To Comment - November 2 [PaEN]
-- DEP Invites Comments On New Air Pollution Permit For Revolution Natural Gas Cryogenic Processing Plant In Washington County; Plant Suffered Major Explosion, Fire In 2022 [PaEN]
-- DEP Posted 82 Pages Of Permit-Related Notices In November 2 PA Bulletin [PaEN]
Related Articles - Gas:
-- DEP Discovers Wastewater Release At Bear Lake Properties Oil & Gas Wastewater Injection Well In Warren County During Routine Inspection [PaEN]
-- Bradford Era: 7-Part Series Details Concerns Residents Of Cyclone, McKean County Have With Catalyst Energy Oil & Gas Wastewater Injection Well [PaEN]
-- Joint Meeting Of DEP Citizens Advisory Council, Environmental Justice Advisory Board Nov. 12 On Oil & Gas Methane Emissions Reductions; Hydrogen Hubs [PaEN]
-- Environmental Quality Board To Consider Proposed Spill Notification Regulation; Blasting; NOx & VOC Corrections Nov. 12 [PaEN]
-- Low-Flow Water Conditions Trigger Big Jump In Susquehanna River Basin Water Withdrawal Restrictions, Most Shale Gas-related [PaEN]
-- Environmental Groups File Notice Of Intent To Sue The Shell Petrochemical Plant In Beaver County For Air Pollution Violations: Similar Action In 2023 Resulted In $10 Million Settlement [PaEN]
-- Gov. Shapiro, Joins 4 Other Governors To Call On PJM To Reform Its Electric Generating Capacity Auction Rules To Prevent Billions Of Dollars In 'Unnecessary’ Costs To Their Residents, Businesses [PaEN]
NewsClips:
-- Post-Gazette - Anya Litvak: As Fracking Turns 20 In Pennsylvania, Towns Consider New Regulations For Distance Between Homes And Well Pads [Cecil Twp., Washington County] [PDF of Article]
-- The Derrick - Randy Bartley: Priority To Plug Old Conventional Oil, Gas Wells Deepens For DEP [PDF of Article]
-- The Derrick - Randy Bartley: Plugging A Problem Abandoned Conventional Gas Well [PDF of Article]
-- Institute For Energy Economics & Financial Analysis: Shell Petrochemical Plant In Beaver County 'Unlikely To Meet Financial Targets'
-- Inquirer: Electric Bills Are Rising In PA, NJ; Governors Want PJM To Help Cut Costs
-- National Fuel Gas Increases Natural Gas Costs 3.7% On Nov. 1
-- Baker Hughes: PA Natural Gas Drill Rigs Increase One To 13 From Last Week, Still Down From 21 On Aug. 23
-- S&P Global: US Natural Gas Producer Coterra Signs LNG Gas Supply Deals With Vitol, UK’s Centrica Linked To LNG Prices
-- Bloomberg: European Natural Gas Prices Post Biggest Weekly Decline Since January
-- Bloomberg: European Natural Gas Prices Drop As Goldman Warns Of Bearish Risks
[Posted: October 28, 2024] PA Environment Digest
No comments :
Post a Comment