PPL intends to construct a new 69/12 kilovolt (Kv) substation and rebuild portions of the adjacent 69 kV transmission line by installing five new foundations and four direct embed steel monopole structures on the existing transmission line and new tap line to the substation.
The existing transmission line parallels the railroad tracks between South Middlesex Road and Old Stonehouse Road.
The proposed transmission line work will include temporary construction access from township roadways and temporary work pads and pulling pads for pole work.
The substation construction will require one new permanent driveway from South Middlesex Road.
The project will impact LeTort Spring Run (High Quality).
No hearing has been scheduled, but one may be requested.
Comments are due October 19-- 30 days from this notice.
Comments should be sent to DEP Southcentral Regional Office, 909 Elmerton Ave., Harrisburg, PA 17110 or by email to: RA-EPWW-SCRO@pa.gov.
Requests to review the permit application should be made to the File Review Coordinator at 717-705-4732.
Read the entire PA Bulletin notice for more information. (PA Bulletin, page 6199)
DEP Data Center Permit Information
Visit DEP’s Data Center Permit Tracker webpage for information on pending permits for A.I. data center projects established by Gov. Shapiro’s Data Center Executive Order.
The Governor’s executive order requires data center developers to obtain all permits and local approvals before DEP can review any permits for the facility.
To provide information to the state on new data center proposals and whether they meet the requirements in Gov. Shapiro’s Data Center Executive Order, visit the Data Center Feedback webpage.
For more information on environmental programs in Pennsylvania, visit DEP’s website. Submit Environmental Complaints; Click Here to sign up for DEP’s newsletter; sign up for DEP’s eNotice; Like DEP on Facebook, Follow DEP on Twitter and visit DEP’s YouTube Channel.
Related Articles This Week - Permit Notices:
-- DEP Invites Comments On New Water Quality Permit For Amazon Data Services ADS Berwick Data Center In Salem Twp., Luzerne County [PaEN]
-- DEP Issues Section 401 Water Quality Certification For Restart Of Constellation Energy Three Mile Island Data Center Nuclear Power Plant In Dauphin County [PaEN]
-- DEP Invites Comments On Stormwater Permit For PPL Electric JUNI-NEBU 500 kV Transmission Line Project In Perry County To Serve Large Loads [PaEN]
-- DEP Invites Comments On Stormwater Permit For PPL Electric Stonehouse Substation & Transmission Line Project In Middlesex Twp., Cumberland County [PaEN]
Related Articles This Week:
-- PUC Study Warns Rapid Data Center Growth Will Cause PJM Electric Grid To Fail Reliability Standard In 2027, If No Further Actions Taken [PaEN]
-- Report: Winter Heating Oil Costs Expected To Increase Over 31%, Electric By 9%, Natural Gas By 5.8% [PaEN]
-- Federal Motor Carrier Safety Administration Issues National Hours Of Service Waiver For Transporting Gasoline, Diesel Fuel In Response To Global Fuel Supply Chain Disruptions [PaEN]
-- PJM Interconnection Issues Maximum Generation, Load Management Alerts For Sept. 17 For Entire Service Area Due To Hot Weather, 35,000 MW Of Maintenance Outages; Requested DOE Emergency Order [PaEN]
-- PJM Interconnection Maximum Generation Alert Remains In Effect For Sept. 18; Emergency Demand Response Customers Activated On Sept. 17 To Increase Reserve Generation Because More Generation Went Offline [PaEN]
-- PPL Electric Files Proposal With PUC To Make Electric Transmission Costs More Transparent, Establishes New Way To Assign Costs Incurred For Data Centers To Those Customers [PaEN]
-- PA GreenGov Council, Penn State Sustainability Host 2026 Sustainability Week Oct. 5-9 With Timely Webinars Exploring The Future Of Pennsylvania's Energy [PaEN]
-- Solar Energy Canopy Installation Nearly Complete At PA Turnpike’s Headquarters Building In Dauphin County [PaEN]
-- Commonwealth Financing Authority Awards $301,473 Solar For Schools Grant To Allegheny Valley School District In Allegheny County For Installation Of Solar Energy Facility
-- Allegheny County, City Of Pittsburgh, Solar United Neighbors Launch Switch Together To Help Local Homeowners Reduce Energy Costs By Going Solar [PaEN]
-- DEP, PHFA Host Sept. 24 Webinar On New Homeowner Energy Efficiency Loan Program To Reduce Your Energy Costs [PaEN]
-- Report: Winter Heating Oil Costs Expected To Increase Over 31%, Electric By 9%, Natural Gas By 5.8% [PaEN]
NewsClips:
-- Capital & Main - Audrey Carleton: Pennsylvania’s Amazon Data Center Boom Fueled By A Lucrative Tax Break [Will Cost PA Taxpayers $2 Billion In Revenue By 2031]
-- PennLive - Charles Thompson: PUC Report Warns Of More Power Outages As A.I. Data Centers Surge In Pennsylvania
-- WHYY - Sophia Schmidt: A.I. Data Center Growth Could Mean Blackouts In Coming Year, PA PUC Report Says
-- The Center Square: PUC Warns A.I. Data Center Demand Threatens Electricity Grid Reliability
-- Tri-State Alert: PA Senate Republican Leader: Legislature Needs To Pick Up Slack From Prior Governors And Boost Energy Production [Nothing About Pausing Data Center Development Causing Spike In Demand]
-- PA House Republican Policy Committee Hearing: ‘Unleash’ Pennsylvania Natural Gas To Lower Costs, Strengthen Reliability [Nothing About Pausing Data Center Development Causing Spike In Demand]
[Posted: September 18, 2026] PA Environment Digest

No comments:
Post a Comment